Highway 27 Construction Update – July 18
We’re in the home stretch! Crews are making great progress across the corridor — with concrete work, paving, and landscaping nearly wrapped up. Thank you for your continued patience as we move into the final stages of this project. Progress to date: · Bridge area: Curb removal on the northeast side is now complete, and the northwest side has been excavated, graded, and prepared for new curb and asphalt. · 2nd Street (north side): All grey and coloured concrete has been placed, and the area is now ready for the final patterned concrete pour; the first two lifts of asphalt are complete. · 2nd Street (south side): Landscaping and installation of the signage and railing are complete. · 4th Street (north side): All concrete is poured, including patterned sections; the second lift of asphalt has also been placed. What’s coming in the next two weeks: · Bridge area: On the northwest side, curb and gutter will be graded and formed in the next couple of days, followed by concrete pouring and asphalt paving soon after; a new steel barrier will be installed early next week while the bridge remains open with flaggers in place to help keep traffic flowing. On the northeast corner, curb and gutter work is expected to be completed next week, followed by installation of the new steel barrier. The bridge is expected to open to two way traffic on July 22, weather permitting. · 2nd Street (north side): Final patterned concrete is expected to be poured this weekend. · 3rd Street (north side): Signage installation is underway and will continue through the week. · 3rd Street (south side): Landscaping, coloured concrete work, and sign installation are expected to begin within the next few days. · 4th Street (north side): Landscaping and final signage installation are planned for this week. · 4th Street (south side): Crews will begin installing signs, boulders, and bollards over the coming days. · Highway 27: The final lift of asphalt is scheduled to be placed on the north side between 1st and 4th Streets by the end of the week, with paving of the remaining sections continuing into next week. Line painting will begin early next week on the north side and carry through to the rest of the highway by the end of the month. Crews are aiming to open Highway 27 to two-way traffic on August 1, weather dependent. 🚨 Reminder: Temporary Vehicle Size Restrictions in Effect Temporary size restrictions are currently in place through the project area:
While some work is still ongoing, much of the heavy lifting is done and crews are shifting their focus to finishing touches. Thank you again for your continued patience — we’re almost there! |
REVISED VEHICLE SIZE RESTRICTIONS, STARTING JULY 14, 2025
The following vehicle size restrictions will be in place starting July 14, 2025, for a period of two weeks.
|
Highway 27 Construction Update – July 10
With several major milestones now behind us, construction
crews are making steady progress across the corridor. From paving to concrete
work, activity remains high in multiple areas as we continue to move closer to
project completion. Thank you for staying informed and navigating safely around
the construction zone.
Progress to date:
What’s coming in the next two weeks:
🚨 Reminder: Temporary Vehicle
Size Restrictions Coming Soon
Starting July 14, for a period of two weeks, temporary size
restrictions will apply to oversized vehicles through the project area:
As always, we’re working hard to minimize disruption while completing as much work as possible in the coming weeks. We appreciate your ongoing patience and attention to posted signage, lane shifts, and detours. We’ll continue to share updates here and at sundre.com/p/hwy-27 as the work progresses. |
Highway 27 Construction Update – July 4
Thanks to everyone for your continued patience as we move
through the busy summer construction season. We’re making great progress on key
areas throughout the project, with more visible improvements completed each
week.
Progress to date:
What’s coming next:
🚨 Reminder: New Vehicle
Size Restrictions Coming Soon
Starting mid-July, for a period of two weeks, new size
restrictions will apply to oversized vehicles through the project area:
Thank you again for your ongoing patience and cooperation. With major components like the bridge open and concrete work nearing completion, we’re making steady progress toward wrapping up construction and restoring full access. We'll continue to keep you informed as we move into the final stages of the project |
Project Overview
Detour Route & Vehicle Size Restrictions
REVISED VEHICLE SIZE RESTRICTIONS, STARTING JULY 14, 2025
The following vehicle size restrictions will be in place starting July 14, 2025, for a period of two weeks.
|
Project Background
Highway 27 plays a key role in supporting the growth and development of several central Alberta communities. Within the Town of Sundre, Highway 27 is designated as an Over Sized Over Weight (OSOW) route and is a key contributor to Alberta’s High Load Corridor.
Alberta Transportation and Economic Corridors (TEC) has planned improvements to Highway 27 through the Town of Sundre, from the east boundary of the Town to the west boundary. The improvements are designed to support safer, more efficient travel through this area and enhance pedestrian safety.
The planned improvements include:
· Single lane roundabout at Highway 27/22/584/Range Road 54 (10th Street) intersection
· Permanent mini roundabouts at 2, 3 and 4 Street (West) intersections
· Intersection improvements at 1 Street (West) (right-in, right-out)
· Pavement rehabilitation, improvements to curbs, gutters, sidewalks, access management and lighting.
Following public engagement in 2022, additional improvements were identified including intersection upgrades at Centre Street, the Red Deer River bridge approach slabs, signalization of Highway 760 intersection, waterline relocations and additional lighting improvements.
The temporary mini roundabouts installed as a pilot project in 2017 have been assessed and deemed effective in improving both traffic flow as well as pedestrian safety. As such, TEC have directed the installation of permanent roundabouts along Highway 27 at 2 Street, 3 Street and 4 Street in 2024.
The anticipated timeline for the TEC improvements to Highway 27 is as follows:
- 2025 (January to February) - Miscellaneous construction activities (e.g. utility relocation, clearing of construction laydown area – in the northeast quadrant of Hwy 27/22/584/10th Street Intersection
- 2025 (March to October) – Construction activities for Hwy 27 Improvements
- 2025 (November) – Hwy 27 Construction completion (contingent on weather)
For more information about the Highway 27 improvement project, visit Highway 27 Improvements (Sundre) | Alberta.ca
Contact Information
If you have questions about this year’s construction work, please contact hwy27@sundre.com.
If you are interested in receiving project updates, please fill out the form below: