Toolbar

  • font sizeA
  • A
  • A

HWY 27 Improvements


 Highway 27 Construction Update – April 11

We’re continuing to make steady progress on the Highway 27 improvements. Below is an update on what’s been completed and what’s coming up next.

Progress to date:

  • The detour road is fully open for westbound traffic on Highway 27. Please slow down and drive carefully through this residential area.
  • Concrete curb work is complete at Highway 27 and 5th Street and in front of Friesen’s.
  • Sidewalk and asphalt removal is done on the north side of 3rd Street.
  • Concrete work and electrical upgrades are ongoing at 2nd Street, with sidewalks now poured from 1st Street to the Burger Baron. The pedestrian signals have been removed at this location.
  • Preparations are underway for sidewalk and road work on Centre Street, and the road has been prepared for gravel.
  •  Cleanup has begun at the intersection of Highway 27 & 760.

What’s coming next:

  • Pouring of sidewalks and curbs will continue in several areas including Highway 27/760, Centre Street, 2nd Street, 3rd Street, and 4th Street.
  • Electrical and streetlight work is ongoing throughout 2nd, 3rd, and 4th Streets.
  • Road grading and gravel placement will happen on Centre Street, 2nd Street, and 4th Street.
  • Asphalt paving for the Centre Street turning lane is expected to begin next week.

·         The mini roundabouts will start to take shape toward the end of the month, with crews forming the roundabouts at 2nd, 3rd and 4th Streets.

Please follow all signage and drive carefully. We appreciate your continued patience as we work to complete the Highway 27 improvements. 



 

Highway 27 Construction Update – April 7

Work is progressing well on Highway 27! Here’s a look at what’s been done and what’s coming up next.

Progress to Date

  • The detour road opened on schedule April 3 for westbound traffic. Drivers are reminded to slow down and use caution as the route runs through a residential area.
  • Revised traffic and pedestrian accommodations are now in place at 2nd and 4th Streets NW.
  • The electrical conduit crossing at Centre Street is complete, with electrical on going.
  • Grading, placing gravel and formwork is ongoing at the south side of 1st Street NW, to the access to Burger Baron.
  • Sidewalk and curb have been poured on the south side of 5th Street NW, at the creek.
  • A mountable curb at the barrier wall on 9th Street NE is complete.

What’s Coming Next:

  • Highway 27 & 760 intersection: Cleaning, grading, gravel placement, and concrete forming and pouring at the corners of the intersection. Landscaping and repairs will take place mid-April.
  • Centre Street: Grading and forming curbs and sidewalks.
  • 4th Street NW: Installation of streetlight bases continues.
  • Sidewalk preparation, including forming and pouring of concrete, will be taking place throughout the coming week at 2nd, 4th, and Centre Streets.

⚠️ Reminder: Speed limits stay at 30 km/h in the construction zone — even if crews aren’t working — and fines double in construction zones. Stay safe and be patient. Thank you for your continued support!



 

Highway 27 Construction Update - March 31

Despite the snow, significant progress has been made on the Highway 27 project as crews prepare for the upcoming detour road switch planned for the evening of April 3.

This detour will redirect westbound traffic up 1st Street NW, along 1st Avenue NW, and reconnect to Highway 27 along a new road just past 5th Street NW. Eastbound traffic will continue to use Highway 27.

Motorists are asked to slow down and drive with caution as this detour passes through a residential area with pedestrians and children.

Progress to date

·         Detour road: Paving and line painting are underway, with barriers and streetlights installed. Final paving for 5th Street NW and part of 1st Street NW is scheduled for this coming week. 

·         Centre Street: All streetlight conduits and signal bases have been installed. 

·         Highway 27 & Highway 760: Excavation work, pedestrian signal removals and conduit crossings have been completed. Thank you for your patience with the overnight work and lane restrictions.

·         Concrete work: Curbs and sidewalks have been poured at 5th Street, near Dairy Queen.

Sidewalks and grading work has wrapped up on Centre, 2nd, and 4th Streets, and sidewalk grading from 1st Street to 2nd Street is now underway. 

What to expect

·         Highway 27 & 5th Street: Final paving, grading, and asphalt work.

·         Detour road: Barrier installation and detour opening for westbound traffic on April 3.

·         Sidewalks & concrete: Ongoing curb and sidewalk work near Friesen Supermarket, 5th Street, and 2nd Street (Burger Baron area).

·         4th & 2nd Streets: Underground utility work, asphalt removal, and streetlight installations.

Oversize and overweight restrictions

Once the detour road is in place, vehicle size restrictions will apply. Vehicles exceeding 6.0 metres in width will require a permit for access.

  • Restrictions: Max 6.0 m wide, 5.3 m high, and 45 m long (westbound), with a max wheel track width of 3.2 m. Eastbound limits are 6.0 m wide, 9.0 m high, and 5.2 m wheel track width. Drivers with loads larger than 4.0 metres are asked to contact PME.
  • Special Accommodations: Available on Tuesdays & Thursdays between 10 PM - 6 AM. Drivers must contact PME in advance to arrange passage.
  • Absolute Maximum Load Limits: 14.0 m wide, 9.0 m high, 6.0 m wheel track width.

For more details and PME contact information, visit Town of Sundre - HWY 27 Improvements.


 Project Overview 

Detour Route & Vehicle Size Restrictions

 

 

 

 

Project Background

Highway 27 plays a key role in supporting the growth and development of several central Alberta communities. Within the Town of Sundre, Highway 27 is designated as an Over Sized Over Weight (OSOW) route and is a key contributor to Alberta’s High Load Corridor.

Alberta Transportation and Economic Corridors (TEC) has planned improvements to Highway 27 through the Town of Sundre, from the east boundary of the Town to the west boundary. The improvements are designed to support safer, more efficient travel through this area and enhance pedestrian safety.

The planned improvements include:

·       Single lane roundabout at Highway 27/22/584/Range Road 54 (10th Street) intersection

·       Permanent mini roundabouts at 2, 3 and 4 Street (West) intersections

·       Intersection improvements at 1 Street (West) (right-in, right-out)

·       Pavement rehabilitation, improvements to curbs, gutters, sidewalks, access management and lighting.

Following public engagement in 2022, additional improvements were identified including intersection upgrades at Centre Street, the Red Deer River bridge approach slabs, signalization of Highway 760 intersection, waterline relocations and additional lighting improvements.

The temporary mini roundabouts installed as a pilot project in 2017 have been assessed and deemed effective in improving both traffic flow as well as pedestrian safety. As such, TEC have directed the installation of permanent roundabouts along Highway 27 at 2 Street, 3 Street and 4 Street in 2024.

The anticipated timeline for the TEC improvements to Highway 27 is as follows:

  • 2025 (January to February) - Miscellaneous construction activities (e.g. utility relocation, clearing of construction laydown area – in the northeast quadrant of Hwy 27/22/584/10th Street Intersection
  • 2025 (March to October) – Construction activities for Hwy 27 Improvements
  • 2025 (November) – Hwy 27 Construction completion (contingent on weather)

For more information about the Highway 27 improvement project, visit Highway 27 Improvements (Sundre) | Alberta.ca

Contact Information

If you have questions about this year’s construction work, please contact hwy27@sundre.com.

If you are interested in receiving project updates, please fill out the form below:

  • Info! Required Fields *

  • Yes No