REVISED VEHICLE SIZE RESTRICTIONS, STARTING JULY 14, 2025
The following vehicle size restrictions will be in place starting July 14, 2025, for a period of two weeks.
|
Highway 27 Construction Update – Aug 6
We’re in the final stretch! Crews are completing the last
elements of the Highway 27 improvements. Work this week is focused on final
paving, line painting, landscaping, and cleanup to get everything ready to wrap
up by next week.
Progress this past week:
What’s coming next:
With work wrapping up this weekend, we're excited to deliver safer, more efficient travel through the area for everyone who lives, works, and visits Sundre. We appreciate your patience and support every step of the way. |
Highway 27 Construction Update – July 31
Crews have made significant progress across all parts of the
project, and we’re gearing up for the finish line. With major paving and line
painting now complete in several areas, we’re getting ready to reopen Highway
27 to two-way traffic by Friday evening (weather permitting). Landscaping,
finishing touches, and site cleanup are still ongoing, but the biggest
disruptions are almost behind us.
Here’s a quick look at what’s been completed and what’s
coming next:
Progress to date:
What’s coming in the next two weeks:
Thanks again for your patience throughout this project.
We’re almost there!
|
Project Overview
Detour Route & Vehicle Size Restrictions
REVISED VEHICLE SIZE RESTRICTIONS, STARTING JULY 14, 2025
The following vehicle size restrictions will be in place starting July 14, 2025, for a period of two weeks.
|
Project Background
Highway 27 plays a key role in supporting the growth and development of several central Alberta communities. Within the Town of Sundre, Highway 27 is designated as an Over Sized Over Weight (OSOW) route and is a key contributor to Alberta’s High Load Corridor.
Alberta Transportation and Economic Corridors (TEC) has planned improvements to Highway 27 through the Town of Sundre, from the east boundary of the Town to the west boundary. The improvements are designed to support safer, more efficient travel through this area and enhance pedestrian safety.
The planned improvements include:
· Single lane roundabout at Highway 27/22/584/Range Road 54 (10th Street) intersection
· Permanent mini roundabouts at 2, 3 and 4 Street (West) intersections
· Intersection improvements at 1 Street (West) (right-in, right-out)
· Pavement rehabilitation, improvements to curbs, gutters, sidewalks, access management and lighting.
Following public engagement in 2022, additional improvements were identified including intersection upgrades at Centre Street, the Red Deer River bridge approach slabs, signalization of Highway 760 intersection, waterline relocations and additional lighting improvements.
The temporary mini roundabouts installed as a pilot project in 2017 have been assessed and deemed effective in improving both traffic flow as well as pedestrian safety. As such, TEC have directed the installation of permanent roundabouts along Highway 27 at 2 Street, 3 Street and 4 Street in 2024.
The anticipated timeline for the TEC improvements to Highway 27 is as follows:
- 2025 (January to February) - Miscellaneous construction activities (e.g. utility relocation, clearing of construction laydown area – in the northeast quadrant of Hwy 27/22/584/10th Street Intersection
- 2025 (March to October) – Construction activities for Hwy 27 Improvements
- 2025 (November) – Hwy 27 Construction completion (contingent on weather)
For more information about the Highway 27 improvement project, visit Highway 27 Improvements (Sundre) | Alberta.ca
Contact Information
If you have questions about this year’s construction work, please contact hwy27@sundre.com.
If you are interested in receiving project updates, please fill out the form below: